IT之家 · IT业界T2·Infra
72 pts
Nvidia's surging AI chip orders are squeezing consumer GPU capacity, with new B300 orders now quoted at 26 to 40 weeks and GB300 at roughly 14 to 26 weeks, pushing most new projects to delivery in Q2-Q3 2027. As a result, Nvidia has begun cutting GeForce RTX 50 series supply, and the RTX 60 series, originally targeted for mass production by end-2027, may slip further. GDDR7 memory output is also constrained as fabs prioritize server DRAM, driving up prices and adding pressure on GPU supply and PC costs.