Rohan Paul (@rohanpaul_ai)T2·Infra
72 pts
Bloomberg data shows US data center developers have announced roughly 90GW of behind-the-meter generation, yet only about 2GW, around 2%, is actually operating. The bottlenecks are structural: a single on-site plant lacks the redundancy of a multi-plant grid, AI workloads swing demand within seconds and can damage on-site generators, and solar-plus-storage would need nearly 1,800 hectares to serve a 100MW Texas data center at 98% availability. Developers therefore treat self-generation as a bridge until grid interconnection arrives, paying over $100 per MWh versus about $90 for grid power.