Rohan Paul (@rohanpaul_ai)T2·78 pts
- About 95% of contracted GPUs at neoclouds like Nscale are not yet running due to power constraints.
- Lead times for high-voltage transformers and circuit breakers exceed 160 and 125 weeks respectively, far outpacing GPU delivery.
- On-site gas power generation cannot bypass queues, with GE Vernova turbine orders booked until roughly 2031.